on 07-06-2010 9:48 AM
Hi,
when iam transferring purchase requisitions from APO to R3, other snp orders are also automatically tranferring to R3 . How to prevent this?
Thanks,
Dhanush
Hi.
Did you try filtering by the ATP category corresponding to your purchase requisition in the transfer settings?
Thanks
Mani Suresh
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
HI Sharath
Can you please recheck and delete the publication settings for In-house production for all the locations that you dont want to get CIFfed across to ECC?
Secondly, you may also want to remove these products relevant integration models so that the relevant receipts are not CIFfed across to APO.
Let me know if this helps.
Rgds, Sandeep
Hi,
I understand you want to stop SNP orders going to ECC.
you have done Immediate Transfer setting for SNP. Therefore orders are getting transferred to ECC.
Did you try to stop SNP orders transfer from APO configuration to SAP ECC ?
IMG > Integration with SAP components >> Integration via APO CIF >> Application Specific settings & Enhancements >>
Enhancements for SNP >> Set up Transfer of SNP Orders to OLTP system >>
Non-VMI .. SNP >> No Transfer
will it help ?
Regards
Datta
Sharath
In the distribution definition configuration , delete all the entries related to publication type "Inhouse production" . This will prevent the planned orders from going to R/3. Since you have the config for publication type "external procurement" the PR's will get transferred to R/3.
Try this in your test system and then make the changes in production
Thanks
Saradha
Go to the following menu path
SPRO> APO>Supply chain planning> SNP> Cnfigure transfer to OLTP systems
Based on your requirement: only transfer SNP generated Purch Reqs and dono transfer SNP generated planned orders to ECC, you have 2 options
Option 1--Immediately transfer SNP generated Purch Reqs and never transfer any SNP planned orders
Config required: (1)SNP( Select Radio Button- Immediate Transfer) (2) Check the " NO SNP PLANNED ORDERS" (3) Check whether the Dist Definition for the plant is maintained for External Procurement
(4) Check the CIF queues and clear or reset the status
Preferred Option2 for future projects in mind--- As this is a global setting, it is better to have periodic transfer set and then use C5 transaction to send the Purch Reqs to R3 using the Filter as Order Type.
This way you are not putting a hard stop for sending the planned orders to ECC as in OPTION 1.
Config Required: (1) SNP( select Radio Button- Periodic Transfer) (2) Run C5 transaction and give in your plant/product selection and APO order type=21(ext Procurement)
Thanks
Kumar
Hi Dhanush
if you are setting the immediate transfer setting in the OLTP transfer option, then the transaction data is trasferred in real time to ECC provided the correct integration models are active. So you can unschedule the job.
Coming back not publish the planned order, as suggested by Kumar and myself, please delete the publication settings for in-house production 031 after selecting the location. This way the planned orders will not be published to ECC.
I hope this helps.
Rgds, Sandeep
User | Count |
---|---|
9 | |
4 | |
3 | |
2 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.