Dear Sir,

I am implementing BCS in my organisation. There is one problem coming that in one Business Area we need to implement BCS and in another Business Area we do not want to implement BCS.

Is their any process through which we can implement BCS in 1 Business Area.

Any thing can be done on Fund Centre and Commitment item basis,

Regards

Tushar

1 ACCEPTED SOLUTION

iklovski
Active Contributor
0 Kudos

Hi,

BCS (and FM itself) is working on the basis of FM area; there is no connection to business area.

For the budget control as such, you can make derivation rules which will not control the budget (or even generate FM documents) for certain business areas - that's possible.

Regards,

Eli

View solution in original post

1 REPLY 1

iklovski
Active Contributor
0 Kudos

Hi,

BCS (and FM itself) is working on the basis of FM area; there is no connection to business area.

For the budget control as such, you can make derivation rules which will not control the budget (or even generate FM documents) for certain business areas - that's possible.

Regards,