on 07-05-2010 3:35 PM
Hi,
The customer asked me if it is possible in WBS control of availability , to check the budget in relation of individual cost items.
I thought about a WBS structure to create a WBE as a container of Primary cost, later Planning the WBS.
When checking availability works, the controll will be more dettailed respect a total control.
Is there a way to optain this kind of control more easyly?
Thank you for attention.
Kind regards.
tanks a lot
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
As Virendra said budgeting is done for values on the WBS elements and not for the cost elements. In addition to this there is an option wherein you can exclude certain cost elements for which you dont require budgeting.
Regards,
Gokul
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Budget control is done on values in the WBS element and not on cost elements
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
102 | |
12 | |
11 | |
6 | |
5 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.