on 07-05-2010 11:26 AM
Hi,
We are creating planned order in APO using CTM planning engine, the planned order is CIFed to ECC for execution.
In ECC planned order is converted into production order and confirmed.
II am not able to change the start date and end dates of the production order in ECC.
Can anyone please help to resolve the above issue and provide a solution regarding the date chnage in ECC and how it would reflect in APO.
Thanks & regards,
Sanjog Mishrikotkar
Hello,
As you are running CTM, APO is now your main system and every scheduling and dat calculations will be based on this system.
I am not sure if there is the possibility to use ECC system to change an order created in APO.
Luiz Giani
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Thanks for the reply,
I our case we are sending the planned orders from CTM run to ECC and in ECC we are converting it into production order and publishing it back to APO.
Now in case some order gets delayed in execution the end date of production order needs to be changed which should reflect back in APO.
Can you please help me understanding how we can resolve this and get the updated peorduction order date from ECC into APO.
Thanks,
Sanjog