Operation based onfirmation in REM

vineeth_varghese
Active Participant
0 Kudos

I am having 3 operations and on the 2nd operation, some testing will be done. This result in identification of component as OK or Not Ok. How can I capture the Not Ok quantity, as I need to have a report for the rework quantity or scrap quantity. I need to link Material, Planned Order and Quantity.

But I am unable to enter the rework quantity in MFBF a sthere is no provision to capture rework quantity in MFBF. If I enter rework quantity through inprocess inspection point functionality, this rework quantity is no where updated in MFBF.

This is mapped thru REM.

Thanks and Regards

Vineeth

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi Vineeth,

I would suggest to have seperate storage location for the rework.

You can select the storage location in MFBF. for scrap you have the scrap option in MFBF. Here the scrap cost will be posted to your cost collector.

For reporting perspective you can use Defect recording through inspection lot, In Quality Notification you will get the linkage of the production version in notification documents.

Kindly check and revert if you need any help.

Regards,

Anil