POC on Network

Former Member
0 Kudos

Hello Everyone,

I have created a network and activities.

I have done cost planning using work centers and also with materials.

I could able to get the plan costs based on this.

I have applied the POC method (Estimation) to activities and run transaction CNE1 and CNE5.

In this report, I could able to get the % value but BCWS and BCWP is not getting calculated.

It is expected to calculate BCWP and BCWS based on the planned cost done for network and % entered in Estimation.

System is not calculating BCWP and BCWS.

The samething is working fine for WBS Elements.

Request you to kindly give inputs on probable reasons / settings

Thanks in Advance

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Dear Parimal.

when POC values get calculated for the network activities but BCWS or BCWP not, then I'd think that the issue is related to setting concerning the EV basis within the customizing for the progress version. If you want to calculate BCWS and BCWP based on the costs of the network activity you have to choose the setting 'Cost plan (active project, annual values)' for the EV basis. If you choose 'Cost plan (active project, overall values)' instead, this won't work for network activities as this setting just takes the overall plan costs into account (planned for WBS elements via transaction CJ40).

So you should check this customzing and run CNE1 again.

Kind regards,

Dirk