Hi Experts,

I have a situation - We have Mitigated users in CC for the Risks we have Identified- As per the concept if the same user go thru AE the risks we have already mitigated should show up as already mitgated risks Correct? Please advice.

Thanks in advance

Guru

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi Guru,

This depends on your configuration. If you don't want to see mitigated risks in CUP then go to configuration -> Risk Analysis and make sure that the checkbox for 'Consider Mitigation Controls' is Checked.

Regards,

Alpesh