Hi Gurus,

Actually we have one scenario in QA in which for one material there are certain specification whose result we will come to know few days later after posting inspection lot in Unrestricted & also after doing UD.

I want to know how to do result recording for that perticular specification after we already did the UD for that lot?

Is it possible after UD?

Is there any additional customization setting nedded?

Thanks in advance.

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi,

You can do this .

Those MIC for which you want to take result after UD .In control indicator of MIC put long term inspection check box on .

So that even after UD of inspection lot , result record for that MIC will remain open for you to take result.

Regards

SANIL

Edited by: Sanil Vadke on Jun 29, 2010 8:53 AM

Former Member
0 Kudos

My question is solved.

Thanks. Sanil for ur heip.