on 06-29-2010 5:10 AM
Hi,
Is there a SAP standard transaction for clocking on and off jobs for a Network Activity? In PP you can clock on and off a job using CO19 but that doesn't work for PS.
Any help would be appreciated.
Regards
Adeel
As I understand, this kind of funcationality is not there in PS becasue in PS all the project activity is not direclty depends upon physical plant resource entiry directly. So, indirectly you can achieve the same via early confimration and extending duration of acitivty etc..
Pelase share if someone have other views.
With Regards
Nitin P.