Hi,

Suppose there is no stock yet available in DC and hence is it possible to confirm quantity out in the future - and beyond cancel date of sales order?

Also can ATP confirm stocks which are after the cancellation of sales order date assuming no stock is there in Sloc?

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

closed

Former Member
0 Kudos

Hi,

Your question is a little bit general - and could be clearer.

There are a number of ways to allow a sales order to commit even there is no current stock. These are all based on the settiings for the ATP check combination assigned to item.

1. If included in the scope of the ATP check, sales orders can commit against future replenishment plans (e.g. production order, PO, reqisitision, planned order).

2. If there is no future replenishment plan, the item can still commit if there is a total replenishmemt lead and this is flagged as relevant in the ATP rule