Project Status Change Date

former_member183901
Active Participant
0 Kudos

Hi!

I wolud like to see the Project Status Changed dates. Which data base table I need to refer?

Thanks in advance.

Regards,

Accepted Solutions (0)

Answers (4)

Answers (4)

former_member183901
Active Participant
0 Kudos

OK

Former Member
0 Kudos

Correlating the tables PROJ and JEST with JCDS and JCDO may help I think.

Thanks and Regards

Former Member
0 Kudos

You may find this information in table JCDO.

former_member183901
Active Participant
0 Kudos

Thanks Nitin, I am asking about Project Level Status date change.

nitin_patoliya
Active Contributor
0 Kudos

I regret that I haven not properly understod your question, you are asking when levels of WBS got changed etc..... Just check If you have appropiate settings in Project profile and other customization in Change profile than check CN60.

With Regards

Nitin P.

former_member183901
Active Participant
0 Kudos

Thank You Nitin. I am finding the change dates in CN60. If I want to get relative Table, how to go about it. The date in CN60 is showing structure PSIS_CHANGE_DOC.

nitin_patoliya
Active Contributor
0 Kudos

It is not given in any standard report/ table, you need to develop some report and that also may not be straight forward to get it. But the same you can get in any PS structure maintenance T Code say Cj20n >Open that WBS> Keep cursor on it> Click on bule I Icon which get displyed on right hand pan > click on first left menu here you will get all the change history.

With regards

Nitin P.