Product Costing with split valuation

Former Member
0 Kudos

Hi,

In our scenarion, we have split valuation for Finished goods with different valuation type.

now with valuation type , we have price control "S" and without valuation type price control is "V'

When i m doing the costing run, system is not pickinng the valuation type. System is updating the standard price without valuation type , where the price control is "V".

Because of this system is not updation the value of the stock as per the standard price.

Is there any way to do the costing run with valuation type specific.

Thanks

Prashant

Accepted Solutions (0)

Answers (2)

Answers (2)

harnish_shah
Participant
0 Kudos

Any updates on this?

waman_shirwaicar
Active Contributor
0 Kudos

Hi,

Regarding the split valuation and standard price :

The cost estimate is created on the header segment and this is Standard SAP design.

If one material has split valuation, standard price will be released only for header segment (valution type blank). You have the possibility to release standard price for in-house production segment, if you set the 'Default'-flag in the customizing transaction for splitted val. (OMWC) for the val. category 'X'.

Alternatively you might create a mixed cost estimate to release prices for each procurement alternative that is associated with a val. type.

The only way to mark and release a standard costing per valuation type is by using the functionality of mixed costing. That means that you have to define a quantity structure category and define a procurement alternative based on a valuation type of your material. Afterwards you have define a mixing ratio for your material and the defined quantity structure category.

Based on this master data (procurement alternatives and mixing ratios) it is possible to carry out a mixed costing, one part of this mixed costing should be a cost estimate based on your valuation type. If you mark and release the mixed cost estimate the system will set the standard price on valuation type level (prerequisite: you have the define the procurement alternative based on the valuation level)

Please refer to NOTE 552486 (FAQ):

"Question 10: In the case of a split valuation, why can the prices only be updated in the internal segment?

Answer:In the initial standard SAP System, only the header segment is calculated and the price is updated only here.However, if the "Valuation type 'in-house production' mandatory" flag is set for the categories in Customizing (Transaction OMWC), it is also possible to update the price in an internal segment.For external segments (procured externally) this does not make any sense in general.However, mixed costings can also be created and updated for several segments via procurement alternatives."

Setting this flag will take impact on materials WITH split valuation in the future. New prices will be released for the in-house segment in addition to header segment in TA CK24.

regards

Waman

Former Member
0 Kudos

Hi

Based on the recommended solution to use mixed costing to mark and release the standard cost estimate to the material at valuation type level, i have tested this recommendation in the SAP system.

However, the mark and release function using CK24 only allow one (1) costing version to be updated to the standard price for only one valuation type. If the material have 2 or more valuation type, how to update the different costing version to the respective valuation type?

I have a scenario below:-

Material XYZ has split valuation which consist of Valuation Type A and Valuation Type B. Both valuation type are using standard costing (S) in the price control.

Using the Mixed Costing approach, we can use different costing version to represent different cost estimate. So, we have created 2 costing version.

Costing version 1 is to represent the standard cost estimate for material XYZ in valuation type A.

Costing version 2 is to represent the standard cost estimate for material XYZ in valuaiton type B.

Hence, when we use CK24 to mark and release the standard cost estimate, system only allow one costing version to be updated to the material master at the valuation type level.

My question is how do we update the standard cost estimate for more than one valuation type for the same material?

Former Member
0 Kudos

Hello Lai,

How are you? Could you please let me know, if you've already found a solution for this issue?

Best Regards,

Georgi