Skip to Content

Archived discussions are read-only. Learn more about SAP Q&A

How to manage work center in Production order

Hi,

I am producing a material having one operation (suppose cutting), which I have mentioned in the routing. I have also mentioned the work center in routing on which cutting operation will be performed. When I make the Production order of 1000 pcs there comes only one work center. But practically, they are producing these 1000 pcs on two different work centers ( 500 on one and 500 on second). How to manage this in SAP.

Kindly help me.

Thanks and Regards,

Yogesh Singla

Former Member