Dear SAP Gurus,
I have a formula in my work center like this:
Quantity x Order Quantity / (7/10) / 314000
Quantity is in Days, Order quantity in Kg.
The activity is costed at 334,89 u20AC a day.
When I am going to test the formula in the work center for 15000Kg and 30 Days, the system gives me 685,620 u20AC:
30 x 15000 x (7/10) / 314000 x 334,89 = 685,620 u20AC, so far so good.
The problem comes in the operation of the routing in the production order because:
30 x 15000 x (7/10) / 314000 = 2,05 Days
This value goes to the confirmation of the operation but I want to confirm 30 Days and not 2,5 Days!
Why is this happen?
Thanks in advamce,
Adelmo Silva
Dear ,
Couple of check for you :
1.Check you ahve proper Standard Vaules in the Work Centre Basic data tab
2.Did you have Formula Key correctly placed in the work Centre Scheduling and Capcity Tab ?
3.Did you have Valid Axtivity Type ass per KP26/KP27 are in place in Costing tab -Work Centre with proper valaididty date .This Activity type is linked with cost centre as well as Fonula Key .
4.What is alternative unit of measure maintained in Material master ?
If you look into the Calcualtion in both cases , Your activity rate : 334,89 u20AC a day is not considerd in calcualtion at production order level. Activity Type is missed out in the Routing -Operation through Woork Centre .
Basically , if you have valid Activity type which contains the Rate (KP26/KP27) , then operation hrs are calcualred based on the Formula Key which u have assinged in the Scheuling or capacity tab in the work centre .This actuvity type should be assinged in the Costing Tab along with Formula Key .
Check this points and come back .
Regards
JH
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear ,
What about Standrad Value Key in Work Centre ?
Generally , you should have Standard Value Key -Set up /Labour/Machine with UOM at Work Cnetre Basic View .Now , this Standard values key uses the Formula Key and Formula Parameters .Formula key Like Setup-SAP001 , Machine -SAP002,Labour -SAP003 should be assinged to the Scheduling and Capacity Tab .If you have your own Forumula key as posted by earlier for Standard Value Key , then you have to assing the same in Scheduling Tab/Capa Tab .
In costing view , if you have Formula Key with proper activity type but with out standard Vaule Key , then Operation hrs will not be calcualted correctly .
So please keep trak on Standrda Value Key-Formula Key and Activity Type in Work Centre
Test in sand box and compare with a standard Work Centre Set up , i think this can be solved .
Regards
JH