on 06-25-2010 1:41 PM
In CK11N when we enter the planned price in material master for the material then the cost estimate should show that cost.it is not showing in the purchase info record.the problem is the material cost is not getting picked up in CK11N.
The problem is not taking the price from purchase info record for calculating the price estimate.
please advise.
Check for duplicate info records in ME1P/ME1L/ME13