Change planning plant in production order

Hi Gurus,

my business scenario is the following:

I have 2 plants that are assigned to 2 different company codes. Plant A (ordering plant) and Plant B (supplying plant).

The users place a sales order on plant A and through MRP with special procurement key 80 the planned order is turned into a production order in plant B.

But in the order confirmation the system tries to post the GR in plant A. Is there a way to change the planning plant of the production order at any time i.e in order creation or order confirmation? Because I need the GR against the production order to be done in plant B. Since the subsequent posting according to the business scenario would be after production, the goods should be sold from Plant A to Plant B via a sales order.

Your help would be greatly appreciated.

Panos

Former Member
Not what you were looking for? View more on this topic or Ask a question