Created Value contract Valid from 13.07.2009 Valid to 2.07.2010 Amount2.121.600JPY

Created Release Order of 12 qty (81.6 JPY each) Amount-979.200JPY (12*81.6 JPY) created on 20.06.2010

BUt in Value contract, its showing

Target value:2.121.600 JPY

Value Released: 1.958.400 JPY ( bUt it should show 979.2 JPY)

The released value is made up of the total of open order and delivery values plus the values already billed to the value contract.

Value Released: 1.958.400 JPY ( bUt it should show 979.2 JPY), why is it so(twice of 979.2 JPY)?.... Pls suggest

Accepted Solutions (0)

Answers (1)

Answers (1)

jpfriends079
Active Contributor
0 Kudos

Hopefully you are aware of Quantity and value contract items cannot be processed together in one document.

Kindly check your billing plan (if your contract is have one).

Also, check Cont. item copy mode in your copy control.

Copy mode for material in value contract item

This indicator specifies how the material in a value contract item may be copied.

This only has an effect if the value contract item should be selected for copying into a new document.

There are 3 ways of controlling this:

' ': no restrictions

'A': the material from the value contract item may not be copied. Here, releases may only activated for other materials.

'B': only the material from the value contract item may be copied and only this material may be released

Thanks & Regards