PP Experts,

We have various groups of labour defined as work center in the system.

We have also defined work center catagory as a person.

In no. of individual capacity field we have updated no. of labours in that work center hence the system is

giving me no. of available hours.

Now my requirement is , in over time not all labours are required only few are there. How can map this in the system.

Thanks in advance,

RG

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

ok

Former Member
0 Kudos

Hi Rajiv

HR module need to be integrated with PP for this requirement