Scheduling Agreement

Dear All,

I have create sceduling agreement 01.06.2010 to 30.06.2010, a pricing procedure with record assin on the agreement, and a 2nd pricing procedure is call in delivery just to incorporate a manual entry for gas pressure, invoice is created with reference to delivery and order. that is all right so far.

please advise me that what type of copying control i should use if lets say price is change on 15.06.2010, currently system call the same pricing as on agreement.

Please advise the accurate one that s very critical for me.

Regards,