on 06-24-2010 10:27 AM
Dear Friends,
I have a requirement for Purchase order Release.
The problem area is in purchase order ... there will be 2 Relase approvals
01 Mr. Abcd
02 Mr. Xyz
After level 1 approval and before level 2 approval ... i want to do some actions.. these actions are related to another product named savvion .
My question is can i stop the document to be edited by 02 ( Mr.Xyz ) untill i complete my process after 01( Mr.Abcd ) has finished his work.
This is to be done on top priority.
Please help me.
Cheers
Jitesh.
Hi,
Yes, We can stop the document to be edited by 02 until 01 has finished his work.
After 01 approved the document need to be correct, go to PO header menu release strategy TAB and 01 approved to be revoked (means double click on the tick mark, it will revoked).
Hope it is useful for you.
Regards,
K.Rajendran
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
107 | |
12 | |
11 | |
6 | |
5 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.