Dear Friends,

I have a requirement for Purchase order Release.

The problem area is in purchase order ... there will be 2 Relase approvals

01  Mr. Abcd
02  Mr. Xyz

After level 1 approval and before level 2 approval ... i want to do some actions.. these actions are related to another product named savvion .

My question is can i stop the document to be edited by 02 ( Mr.Xyz ) untill i complete my process after 01( Mr.Abcd ) has finished his work.

This is to be done on top priority.

Please help me.

Cheers

Jitesh.

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi,

Yes, We can stop the document to be edited by 02 until 01 has finished his work.

After 01 approved the document need to be correct, go to PO header menu release strategy TAB and 01 approved to be revoked (means double click on the tick mark, it will revoked).

Hope it is useful for you.

Regards,

K.Rajendran

Answers (0)