Hi Experts,
I use a standard projet structure (project definition , WBS, elements, networks and activities). The settlement rules are automatically generated from project definition on the WBS element and I active the status SETC on WBS element by the CJB1 transaction.
When I create a new project (for exemple from a template), the system demand to complete the settlement rules for each network (I think it is a standard comportement).
My problem is that the company works with big projects (~100 networks per project).
Exist there a solution to make an automatic heritage/generation of the WBS element settlement rules(parent) on the network (child) ? And so not to have to inform all the rules in the creation of the projects (template) -(100 following screen appears)?
Thanks a lot for your assistance.
herieric
Just Explore option of Settlement stretgy for Netwrok for automatick settlemetn rule generation.
With Regards
Nitin P.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello Nitin,
Thanks for your answer.
I've customize a strategie for determining settlement rules from a WBS element to a network with " Copy settlement rule
of the WBS element" and "Copy settlement rule of the project definition" and affect it to the network type but the settlement rules are not copied on the networks.
Thanks for you help.
herieric
User | Count |
---|---|
93 | |
11 | |
11 | |
6 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.