on 06-23-2010 6:35 AM
Hi
The client has to create a sales order to provide services from 3 different plants.These services are for the coming month/s.The schedule lines are created for the period. service can be actually done from any of the plant as per its max capacity.Accordingly the business areas will be affected in billing.How to show the delivery from different plants at delivery level.
Hi,
Plant will be determined- automatically by following creteria
1. Customer-material info-VD51
2.Customer master
3. Material master
SAP also provides to change Plant at item level-(shipping tab) manually. So AV check/delivery can happen from this plant
Thanks
Chidambaram