Hi gurus,
I'm having a strange situation in our plant. Total replenishment lead time of own-produced part ABC is 10 workdays. But when I create a sales order with 10 pieces of ABC, I always get a scheduled line in 60 calendar days at availability check - saying today (23.06.2010) I create an order and requested delivery date is 20.07.2010, I will get a confirmed delivery on 23.08.2010. I have tried several kinds of material - even newly created one - and they are all the same. But this problem just happens in our plant not the others. I cannot see where I'm getting the problem. Can someone please help? Thanks in advance.
yu
Hi, thanks for your replies. I have already checked the RLT in MRP3 tab at least 10 times - it was good. And I do notice when I make availability check, the scope of list considers everything that need to be considered. But I still think there is something tricky in customizing because I don't see the problem in other plants.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
HI,
1. Please check the cusotmizing in OVZ9. Is "check without RLT" flagged?
2. Please check the material master data. MRP 3 tab -> Tot. repl. lead time.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi
For in-house production, the system checks whether the total lead time is maintained in the material master (MRP 2 view). This is the estimated production time for a material, including all production levels from raw material procurement to final assembly.
So, pls. check your material with your plant in MM0 transactions.
Regards,
Siva
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
91 | |
7 | |
7 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.