Hello Gurus,

The scenariois:

1. Material is batch managed and 03 & 04 types activated.

2. Against a production order, several batches will be generated.

Client requirement is:

1. After the relase of PO, only the first batch will be inspected.

2. After that, if required, 10% of that PO will be inspected (type 03)

3. After all these inspection, RR and UD, next stage will be confirmation of PO and generation of 04 type lot.

Is that possible in SAP? I have my doubts. If we activate 03 type in mat master, it should generate lot for every batch. Is it possible to manage the scenario with 04 type, where next stage becomes stock transfer?

Really appreciate quick help on this.

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi

Anyone pls???

Can we use DMR somehow?

Former Member
0 Kudos

Hi

No input?

former_member42743
Active Contributor
0 Kudos

Sorry. I would say you would have to develop all your own custom sample procedures for this. I don't see any easy way for this to be done in standard SAP.

It would even be difficult if you had one PO for each batch. Maybe others might have some ideas but I don't at this time.

FF