Dear PS gurus,

Confirmation parameter OPST: propose dates is tick.

While scheduling eg: Iam having 3activities

1st activity: starting from 18th june having FS relationship with 2nd activity: duration 5days

2nd activity: starting from 25th june

3rd activity:

when i confirm my 1st activity of 5days which is at 22nd june & reschedule it the system takes dates wrt to confirm date of 1st activity. that comes to 29th june to 2nd activity.

Is this related to confirmation parameter.

Regards,

AHS