on 06-21-2010 4:52 PM
Dear PS gurus,
Confirmation parameter OPST: propose dates is tick.
While scheduling eg: Iam having 3activities
1st activity: starting from 18th june having FS relationship with 2nd activity: duration 5days
2nd activity: starting from 25th june
3rd activity:
when i confirm my 1st activity of 5days which is at 22nd june & reschedule it the system takes dates wrt to confirm date of 1st activity. that comes to 29th june to 2nd activity.
Is this related to confirmation parameter.
Regards,
AHS
Let me elaborate this in a better way:
Assume we have below situation :
Activity 1, start date 18/06/2010
Activity 2, start date 25/06/2010 - FS relation ship with Activity.1 - 5 days
In case Activity 1 confirmed date = 22/06/2010, after rescheduling from within transaction CJ20N, system takes this date into account and as a consequence of that, Activity 2 start date becomes 29/06/2010
Rescheduling from CJ20N transaction should act in the same way as transaction CAT5 with the option "Transfer without dates"'.
Regards,
AHS
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
CAT5 does not do rescheduling, it just updates the actual start and finish date for activity 1. After transfer of actual dates information to project, the project does the rescheduling in CJ20N (either manually or automatically). If you choose the option "transfer without dates" in CAT5, the acutal dates will not be transferred , hence you will not get the rescheduling for next activity.
Hope it is clear now.
Regards,
Mahendra
User | Count |
---|---|
104 | |
12 | |
11 | |
6 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.