Hi,
While doing PGI system showing error as Sales order stock 80 000010 does not exist & Picking quantity shows as 0 with gradeout.Please give me the solution how to rectify this error.
Thanks,
Miku.
This happens in Make to Order scenario where you need to maintain the stock at Sales order level, In MB1C, you might need to select 561 and Special proc type E, Give the sales order number and line item number while updating the stock.
Thank you
Kris
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Thnks,solved
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Check the stock in the MMBE
Post the stock in MB1C for your plant and try to Pick and PGI
Please check and revert
regards,
santosh
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
this problem arises when the requirement type which is assigned to the material does not match.
Kindly check the the requirement type in procurement tab in the sales order.
Once it is set,You have to delete the sales order line item and and save the doc and then do the delivery
Suresh
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.