Transportation Cost for a raw material in ck11n

Dear all,

I have run in ck11n cost estimate for raws materiales of plant B which are manufactured in plant A. I have got to transfer the production cost estimate of plant A, when I execute the ck11n in plant B for this raw material.

But I am trying to add the transportation cost to the cost estimate of this raw material, and I don`t get it.

I try to carry the tranportation cost using overhead cost, but it doesn`t run for raw materials when I calculate its cost estimate in ck11n. The same overhead runs properly when I calculate the cost estimate for a finish producto whose BOM has this raw material.

Please, I need your help. How can I get to carry the transportation cost of the raw material when I execute the ck11n for it?

Thanks very much for your help.

Former Member
Not what you were looking for? View more on this topic or Ask a question