on 06-21-2010 4:23 AM
Hi Gurus,
Just would like to briefly understand, how I can make use of the WBS Element in the Production Order (Assignment tab) to use as cost settling for a production order? How do i automate the WBS Element in the production Order for a set of given parameters? Is there a config I can use to set a profile?
I have a scenario here as below:
I have various types of production orders:
PO 1 = Production A
PO 2 = Production B
PO 3 = Production C
And for each of the above, I will individually have a WBS Element.
PO1 - WBS Element A
PO2 - WBS Element B
PO3 - WBS Element C
And WBS Element A, B and C is a Level 2 WBS Element which are tied to WBS Element Z (Level 1 WBS Element), which will be settled to a project.
Appreciate your kind feedback on the above on how I can make it work by settling the cost to the WBS Element.
Thanks.
Rgds.
hi,
maintain settlement rule in production order receiver as wbse. the actual production cost will be settled to respective wbse.
regards,
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Thanks for the reply, NAG.. Somehow, it is still not allowing me to settle to material from WBSE.. indicating an error that the settlement type MAT is to be set automatically only.. which is usually a default that from PP it will settle to MAT immediately.. but since the sequence is changed here, it is not allowing..
Thanks.
User | Count |
---|---|
91 | |
7 | |
7 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.