Hi Experts,

I want to define public holidays and regenerate work schedule for the specific month in which these holidays encounter. My question is should I do this directly in Production system or in Development and than transport to Quality/Production. I know that both options are available. But which one is the recommended option. If transport option is recommended than how can I transport work schedule to Quality/Production.

Accepted answer will definitely be awarded points.

Thanks,

Waqas Rashid

Former Member replied

Generally, when you generate work schedules, system asks for a transport request to be selected.

If the system did not ask for the request, you need to go to SE01, and manually create a request which has the following object:

R3TR TABU T552A -> where the key is : client number, employe groupng, public holiday calendar&personnel area grouping, Work schedule rule YYYYMM.

Hope this helps