Dear SAP Friends,

Currently for Sales orders & Deliveries, we have ATP Check (Allocation Check + Product Check) happening in APO-GATP. We would like to turn-off ATP check in APO-GATP, instead want to do only Inventory Check in ECC locally.

We want to do above for few particular model/plant combinations and not for all model/plant combinations. Meaning APO-GATP will still be used for many other APO relevant Model/Plant combinations.

What are the changes required to CIF Integration models u2013 Salesorder+ATP Check, or any other IM. Any changes specific to material master in ECC - like MRP Controller, ATP Group, Strategy Group or any config changes on APO side.

Please guide me with stepwise instructions.

Appreciate your help.

Thank

Satish

Edited by: SatishW on Jun 18, 2010 9:33 PM

Accepted Solutions (0)

Answers (4)

Answers (4)

pavan_verma2
Contributor
0 Kudos

Hi ,

just remove Plant and Material combination from ATP CHECK Integration Model,

No need to to do anything ATP Customizing, This is used to transfer ATP configuration in the beginning only, do not activate it otherwise you will loose all of your APO configuration of check instructions etc.

Thanks,

Pavan Verma

Former Member
0 Kudos

Hi Satish,

Please check the below

1) Check the availability check in MRP3 view of material master

of R/3

2) Check the ATP group field, check mode in ATP field of APO

product master

3) Check the ATP customizing under material indepdent objects

fields in CFM1 for deactivation

Regards

R. Senthil Mareeswaran.

Former Member
0 Kudos

HI Satish,

You just have to remove the product-Location combination from the ATP check integration

Regards

Vaibhav

digambar_narkhede
Contributor
0 Kudos

Hi Satish ,

I am not an expert on GATP but logically what I can suggest following steps :

1.As you want ATP check to happen in APO for few codes, you will have to Select/Tick 'Material Independant Object' - ATP Customization in CIF IM , so that ATP customizing settings are transferred to APO from ECC.

2. But at the same time you need this ATP check to happen in ECC locally and not in APO for certain products, then in other CIF IM you have to select 'Material dependant objects '- ATP Check where you can set the filter/exclusion on those codes so that the ATP check does not take place in APO.

3. Also like as R/3's backorder processing, in order itself you can set as the ATP check to occur in R/3 and not in APO.

Hope this helps...