'Overlapping' parameters in R/3 routings passed to APO PDSs

Former Member
0 Kudos

I am using APO V7.O connected to R/3 4.7.

In R/3 I have a routing in which I have specified 'required overlapping' and 'min overlap = 0' so that effectively I have parallel operations.

But this overlapping information does not seem to get passed to the APO PDS, where the operations are scheduled in series.

Is this the expected behaviour?

Thanks for any help on this...

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi GroupAPO,

I think to have parallel operations you should have overlap greater than zero.

Which PDS you are talking about? SNP or PPDS. As parallel operations are not supported in SNP. Read SAP note 1079959.

Best regards,

Vaibhav

Answers (1)

Answers (1)

frank_horlacher
Employee
Employee
0 Kudos

please read note 604878 . It covers the operlap.