on 06-18-2010 1:27 PM
Dear all
Is it possible to create a statistical internal order and specify another internal order for the actual postings as opposed to a Cost Centre?
Thank you for your help.
Thanks
Peter
Sincere apologies. My client only posts to Internal Orders with WBS elements for planning and budget perposes. The client wishes to monitor expenses for particular members of staff who are entitled to financial benefits. In order to benefit from avaiabilty control it was suggested either to create an real internal order for each member of staff or alternatively create a statistical order to do this with costs updated in the operational order. I believe the second option in not possible.
Thank you
PRG
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
We are having similar situation and developed Cost to the Company Report. So, in addition to real internal order/cost center posting, we can make use of personnel no column in the transactions for capturing expenditure incured for an employee either of FBCJ, FB60, MIRO, ML81N and of course from HR.
Try this for your requirement and all the best.
Muralidhar
Hi,
I would suggest the forum members to give brief on the Issue rather than giving a solution and asking for limitations or its feasibility. In this case, Please explain the customer requirement and the scenario ..so that forum members can give answers.
Enjoy..
Siva
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
No, you cannot post to two internal orders (one statistical and another real) simultaneously.
Regards,
Eli
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
102 | |
12 | |
11 | |
6 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.