on 06-17-2010 10:42 PM
Hi,
Now I am in SRM 5.0 in SP 16 classic scenery.
When sending a PR of the backend a SC it is generated but the same is not being exhibited in the SOCO.
In the monitor the message is exhibited: BBP_PU367 Shopping center cart &: Error creating the follow-on document
My configurations:
PPOMA_BBP
Extended Attributes:
Product Category = *
SRC SYSTEM = R3CLNT12345
Responsability:
Product Category = *
SRC SYSTEM = R3CLNT12345
SPRO:
defines Backend System goes Product Category
R3CLNT12345 SRMCLNT123
R3CLNT12344 SRMCLNT123
R3CLNT12343 SRMCLNT123
R3CLNT12342 SRMCLNT123
defines Sourcing goes Product Categories
R3CLNT12345 2 SOURCING ALWAYS CARRIED OUT
R3CLNT12344 2 SOURCING ALWAYS CARRIED OUT
R3CLNT12343 2 SOURCING ALWAYS CARRIED OUT
R3CLNT12342 2 SOURCING ALWAYS CARRIED OUT
SOURCE_REL_IND is empty.
HOW CAN I SOLVE THIS PROBLEM?
Rgs,
Pedro Marques
Note 854194 - Attribute missing for currency. Inform system administrator
any clues..
1) Creating a new message
Call Transaction SE91.
Create message for message class BBP_PU.
Release < SRM 5.0 --> Create message 367
Release SRM 5.0 --> Create message 368
Use the message short text "SC No: & Attribute missing for currency."
Set self-explanatory flag and save the message class.
YOU might get detial error in slg1 and check sc number in monitor sc ..too
you might seen all above the same . any queue error in ecc
EPRTRANS cleared?
for all PRs or only some prs?
Any changes you done in the PRs?
Are delivery address entered?
check sc bbp_pd entry for more info. what is the status of sc- error in process
Muthu
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Muthu,
1 - Creating the new message
Message already maid.
2 - YOU might get detial error in slg1 and check sc number in monitor sc ..too
Any error log in SLG1
3 - you might seen all above the same. any queue error in ecc
Any error in ECC.
4 - EPRTRANS CLEARED?
Table is empty.
5 - does all go PRs or only adds prs?
The whole PRs of materials.
Services are going to the SOCO without problems.
6 - Any changes you done in the PRs?
Any alteration in PR.
7 - does it plow delivery address entered?
Yes, my address is associated to the document.
8 - check sc bbp_pd entry goes info lives. what i the status of sc - error in process
Status of SC:
HEADER I1021 CREATED
HEADER I1038 Completes
HEADER I1106 Shopping center cart ordered
HEADER I1129 APPROVED
Other idea?
Thanks,
Pedro Marques
Hi
Are you using any SRC determine badi.
or
you need to llok specific configuration on material group settings.
or
add new entry for new product category
sourcing carry out for items without sos.
let us see it IS PUSHING to cockpit or not?
HOPE YOU seen your cart in monitor sc with status ERROR IN PROCESS
Muthu
Problem doesn't happen plus, problems in the master data of the material.
Tks,
Pedro Marques
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.