on 06-17-2010 7:04 PM
Hi,
We have created a process order with Production plant PRP and Planning plant PLP.
Process order header is : PH
process order component is :PC
As per the data , batch to be used for the component PC in the production plant PRP is B and the same batch is available for the header PH in the planning plant PLP .
Now we have set teh deletion flag for the batch B for the material PH in the planning plant PLP .
But still when we try to release the process order created as production plant PRP , planning plant PLP with Header PH and Component PC ( for which batch assigned is B) system says release is rejected due to the below mentioned error.
"Batch B for material PH iin plant PLP already exists"
Can you please provide inputs how to resolve this ? we are ready to remove batch from PLP
regards,
MADHU KIRAN
marked as answered
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Madhu
Planning plant is one in which, after order execution, the goods receipt takes place for the material produced (Header Material) after execution of the order in production plant.
since you marked the deletion flag for the batch and not deleted hence system is showing the error, as batch is already existing
Regards
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
85 | |
7 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 | |
2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.