Budget control for automatic Purchase orders

Former Member
0 Kudos

Hi All,

We are facing problem in budget availability check for automatically generated Purchase orders through MRP run.

We are able to control the budget check for manual Purchase orders but how can we control budgets for automatically generated Purchase orders.

we are using IM budgeting for orders.

Please let me know your valuable inputs for the above issue.

Thanks in advance.

Regards

Nagesh

Accepted Solutions (0)

Answers (1)

Answers (1)

iklovski
Active Contributor
0 Kudos

Hi,

You have to run FM_MRP_PR transaction in order to transfer MRP documents to FM for budget control.

Regards,

Eli

Former Member
0 Kudos

Thanks Eli,

We are using IM..

what u said is for FM

does it work for IM also...??

Regards

Nagesh

iklovski
Active Contributor
0 Kudos

For CO budget, POs, even from MRP, should consume the budget... If it does not happen, check whether these POs create CO documents at all.