CM21 Strategy Profile with Setup Optimization but consider the requirements

Former Member
0 Kudos

Dear guru.

A question about strategy profile in CM21

The system Is able to execute an automatic dispatch that optimize the setup time of the production order but also consider the requirements date in order that the production orders dispatched can cover the requirements without delay ?

Thanks In advance

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Thanks for your reply.

A technical question.

If I filled in strategy profile in dispatching control view the flag setup time optimization and operation date check and try to dispatch the production orders , which is the behavior of the system ? It consider both or assign a priority to one of two activity ?

Thanks.

former_member196530
Active Contributor
0 Kudos

Based on the operation schedule start and schedule finish date , set up optimisation happened cosidering work center avaialable capacity and overload .

are you using APO PPDS in your business process ?

regards

JH

Answers (2)

Answers (2)

Former Member
0 Kudos

I'm not using APO PPDS. Whose are the differences in this process between APO-PPDS and PP-CRP ?

Thanks.

former_member196530
Active Contributor
0 Kudos

Dear ,

The system Is able to execute an automatic dispatch that optimize the setup time of the production order but also consider the requirements date in order that the production orders dispatched can cover the requirements without delay ?

To answer to your query I would rather say that any operation under an work centre have Execution time =Set up time +Processing Time +Tear Down Time and also Inter operation time -Que time , Wait Time , Move Time .

Now when you dipatch the operation in CM21 , it cheks the available capacity on that date and also compare with the total operation timimngs within schedule start and schedule finish date and then dispach automatically if work centre is not overloaded otherwise it will pop up with a Scheduling Logg or else it will appear with an window that will show u Date , Work Centre , Operation , timie so that you can change according to WC load n availablity in alternate date .So In the strategy prfile if you click Display dates while dispatching u can obseve the same .

Now total production order schedule start and schedule finsihe date will be considered and it will automatically chage as per the WC availabli capaciy while automatic dispatch .But u need to SAVE that to observe the changes in CM21.

Hope it is clear

Regards

JH