Hi,
I have a situation in which Purch Orders are getting priority over stock when I use CTM with Fixed Pegging.
However when I run CTM with Dynamic Pegging, Stock gets higher priority.
Is there a way to give higher priority to Stock over Purchase Orders even when I run CTM with Fixed Pegging. Thank you
Regards
Manotosh
Hi ,
Did you try to use search strategy with Supply Category ?
The search strategy specifies the sequence in which Capable-to-Match planning (CTM) consumes receipts and supplies, and creates new orders.
Regards
Datta