WIP calculation and WBS settlement

venkatesh_kulkarni1
Active Participant
0 Kudos

Hi,

its customer type project....

1) collecting cost in different WBSE... from lower level WBSE to higher WBSE settlement Rule.

Higher level WBSE is Billing WBSE and settlement to PSG.

2) calculating WIP - KKA2

3) WIP calculation and settlement status dependant ... "REL" system does settlement correctly

4) when my project status is TECO - system is not reversing the WIP which was calculated and posted earlier, and final settlement to PSG is not happening.

Venkatesh

Accepted Solutions (1)

Accepted Solutions (1)

0 Kudos

Hi,

WIP is calculated based on the RA key. RA key is setup for each status like REL, TECO, etc. which contains the parameters of structure selection, valuation method etc.,. Please check the correspoding RA key.

Regards,

Harish