Hi,
When we release process order by converting planned order through setting conversion indicator in RRP3. Though we have configured auto release in ECC orderis in created status. Also status RELR(release rejected) is appearing. when I go and manually release it it it getting released.
We checked following things.
Application log in SCM-/SAPAPO/C3-No logs
Application logs in ecc-CFG1-No logs
Cor2- logs for order release- no release logs.
It is not happening all the orders it is happening only for few cases. Any clue?
Regards,
Santosh
hi Santosh ,
Please check the if the master data in R/3 and APO is consitent-the PPM of the APO PPDS planned orders(avl for conversion) has the same production version(valid BOM routing etc) as available in R/3.
Thanks ,
Digambar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
7 | |
4 | |
3 | |
2 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.