Hi all,

How it is possible to charge the material cost to another activity?

The material has GR for the activity A but we require the cost in the activity B (Activities are in same network)

Is it possible to charge the material to this activity (Without PR creation).

Regards, Madhusudan Patil

Accepted Solutions (0)

Answers (1)

Answers (1)

former_member203098
Active Contributor
0 Kudos

hi,

txn kb15n select the scrn var as wbselement/network and enter the sender wbse,network,activity no,costelement and amount.

enter the data for receiver also. with this you can transfer the material cost from one activity to other.

regards,