on 06-11-2010 11:28 AM
Hi ,
Can anyone explain the process STO with WM with shipping and transportation?. What are all the config needs to be done for shipping and transportation?
Regards,
abi
<STO with shipping>
[1]
Please set shipping data for the receiving plant and supplying plant.
img -> mm -> purchasing -> PO -> set up stock transfer order -> define shipping data for plant.
receiving plant <> ship to party
supplying plant <> sales area.
[2]
Please assign delivery type and checking rule.
img -> mm -> purchasing -> PO -> set up stock transfer order -> assign delivery type and checking rule.
[3]
Maintain shipping point determination:
[4]
Maintain and assign confirmation control key (if you are using two step STO and want to post GR via inbound delivery).
This is the same as normal PO.
==========================================================
WM and transportation.
This is basically the same as normail WM and transportation.
Once outbound delivery (replenishment delivery) is created, the process is the same as normal outbound delivery.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi
STO With WM managed plants nothing much difference.
As a normal process of creating STO, then Supplying plant will deliver the material, While doing the PGI, it will ask you to create a TO and confirm the TO. (This is for WM mamaged plants)
Same way for GR aslo ( WM managed plants)
Check it out
Thanks
Raman
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
107 | |
12 | |
11 | |
6 | |
5 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.