offset relationship

ansar_shaikh2
Contributor
0 Kudos

Dear PS gurus!

When we make relationship between two activities and define offset relationship in minus days. It does not show the figure in graphic display.

eg: 10-

the system is not showing 10- inthe graghical display.

When we give Time interval between relationship for networks in minus, it does not display minus in graphical mode.

Is there any setting/customizing for the same????

Regards,

AHS

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi

Please go in the network graphic and click on the relation ship and give the offset as 10- and the try saving it.

Regards.

Varaprasad.

ansar_shaikh2
Contributor
0 Kudos

Iiam trying the same....but in grahical area its not showing minus sign. Need to raises OSS i think so...no reply coming from this site.

Regards,

AHS

ansar_shaikh2
Contributor
0 Kudos

raised OSS, since its an SAP bug.

closing this thread.