on 06-10-2010 12:49 PM
Dear PS gurus!
When we make relationship between two activities and define offset relationship in minus days. It does not show the figure in graphic display.
eg: 10-
the system is not showing 10- inthe graghical display.
When we give Time interval between relationship for networks in minus, it does not display minus in graphical mode.
Is there any setting/customizing for the same????
Regards,
AHS
Hi
Please go in the network graphic and click on the relation ship and give the offset as 10- and the try saving it.
Regards.
Varaprasad.