Negative commitment - PBC earmarked document

Former Member
0 Kudos

Hi,

We have a scenario wherein PBC will generate precommitments and commitments with negative values. We created two new document types that will accept negative values and mapped them to PBC in the config for FM (FM-HR integration -> PBC). Now when we re-run PBC we are still getting the same error. Can one of you please let me know what other areas to look for to resolve this?

Thanks.

PSM

1 ACCEPTED SOLUTION

RCP
Advisor
Advisor
0 Kudos

Hi,

Have you already reviewed the OSS note 1070726? Maybe this note can help you.

Regards,

Rafa.

View solution in original post

2 REPLIES 2

RCP
Advisor
Advisor
0 Kudos

Hi,

Have you already reviewed the OSS note 1070726? Maybe this note can help you.

Regards,

Rafa.

Former Member
0 Kudos

Hi Rafael,

Yeah we did look at the note - we had to make an entry in one of the HCM table. Once we did that, the issue got resolved.