on 06-08-2010 10:54 AM
I have one project, budget 100K USD, 10% tolerance limit, it is already used by PO1 20K, leftover is 80k, I have another canceled PO2, with amount 30K, normally, when PO2 is cancelled, it should not hold any budget, now I have another PO3, with 85K.
but i can't raise that PO3, 85K<80+100*10%, it should be able to raise, why system not allow me to raise PO3?
it seems the cancelled PO2 still consume the budget, how to remove budget by PO2(which is canceled)?
it could be because your PS data is not getting updated / refreshed for some reason
try after running CJEN, CJBN and RKANBU01