Transport Update

Dear All,

We are doing OS/DB migration(SAPR3 4.6C - 4.6D kernal)-(Windows 2003/Sql2000). We are in the process of Rehearsal phase1 now. We build the PRD server(rehearsal1) and created QUA (Rehearsal) system copy of PRD server.

In Rehearsa1 PRD server we did changes on

Z programs & varients(around1000) and created a transport request(XXXXXXX).

Now we have to update the same Z programs & varients(around1000) changes in QUA(Rehearsal) server too.

Please let me know the way to update the transport request ((XXXXXXX) from PRD Rehearsal1 system to Qua (Rehearsal) system.

Thanks

Malai