MB21 No Cost Updation

Former Member
0 Kudos

Hi Experts

We are trying to reserve material using MB21 against WBS but after reservation no plan cost updated? Please tell me if anything is missing?

Atif

Edited by: Virendra Pal on Jun 8, 2010 8:56 AM

No capitals please - title corrected

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

I agree with Ahmed. Thanks for your reply...

former_member203108
Active Contributor
0 Kudos

Manual reservation will not update cost in project. If you plan it through network activities by assigning material to it, then you can see the cost in project.