We have a requirement to sell two CTNs bundled into one new CTN. Details of the requirement are as below:

Advise solution to this in terms of:

u2022 Material master creation (CTN3)

u2022 Conversion process (CTN1 + CTN2  CTN3)

u2022 Unconversion process (CTN3  CTN1 + CTN2)

Please note that:

u2022 There will be no stock transfer of the bundled CTN. Material will be shipped out in unbundled manner, i.e CTN1 & CTN2

u2022 There will be purchase of the bundled CTN. Material will be purchased in unbundled manner, i.e CTN1 & CTN2

u2022 Sales will happen in bundled manner.

u2022 Conversion of the CTN will happen at Plant locations only.

Other requirements

u2022 SAP reporting should be done on a individual (unbundled) CTN level, i.e. CTN1 and CTN2 instead of CTN3.

u2022 Bundling of products will be done across categories.

SO HOW TO GO AHEAD TO IMPLEMENT ABOVE REQUIREMENT..

THANKS

MK

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Try making CTN3 a packaging material, and packing CTN1 and CTN2 into CTN3 as part of the delivery process.

Former Member
0 Kudos

Thanks 2 all