Hi,
how do i change the calendar in SRM when i click on F4 in date field
that it will show me the calendar that i defined in SCAL trans.
thanks,
Michal.
Edited by: michal_zindorf on Jun 6, 2010 8:43 AM
Hi,
Enter the T.code: SCAL
Click on the radio button for selection
click on the EYE
Screen is opened.
Go to Calendar--->change
Try it out
Regards
G.Ganesh Kumar