Hi Gurus,

Is there any control to stop taking UD before result recording

Please suggest

Regards

buss

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hii,

Explore the User Exit - QEVA001. Check program logic for the evaluation status "5". It's working fine.

with regards,

Answers (3)

Answers (3)

Former Member
0 Kudos

How to set the User Exit

Former Member
0 Kudos

Hi

Do step by step as explained in the article. Its quite easy.

[http://www.sdn.sap.com/irj/scn/go/portal/prtroot/docs/library/uuid/20fbc091-ea3a-2b10-f0a3-877ffbf36436?quicklink=index&overridelayout=true]

Another option is ask BASIS to use authorization concept Q_INSP_FIN. It will prevent force completion of characteristics, that means you must do RR before UD.

anand_rao3
Active Contributor
0 Kudos

Hello Buss,

Please go through this link. [http://wiki.sdn.sap.com/wiki/display/PLM/SetupofauserprofiletoavoidtheUDpriortoRR]

Regards,

Anand Rao

Former Member
0 Kudos

Hi,

Create a status profile where UD restricted before result recording.

Reg,

Naveen.