on 06-03-2010 8:07 AM
Dear Sir,
We are facing problem related to following scenario :
We have a Production Order having 10 numbers operations . These Operations can happen in parallel or sequential depending upon the circumstances . We have a situation where Operation number 4 is in partial confirmed status and against all other operations (ie Operation number 1 to 3 and 5 to 10 , no work has yet started) .
During the Sceduling in PP/DS , system is treating Operation 1 to 3 as FIXED and not getting scheduled . Only operation 5 to 10 are getting scheduled .
However we desire that all pending Operation must get scheduled .
Kindly help us to guide pl as how can we overcome this issue pl .
Rgds
B Mittal
Hi Mittal,
In APO customisation under PPDS strategy profiles, incorporate
the relevant settings for scheduling mode and scheduling
submode under two different tabs.
Regards
R. Senthil Mareeswaran.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
7 | |
4 | |
3 | |
2 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.